Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) More of Project A's cash flows occur in the later years.
B) More of Project B's cash flows occur in the later years.
C) We must have information on the cost of capital in order to determine which project has the larger early cash flows.
D) The NPV profile graph is inconsistent with the statement made in the problem.
Correct Answer
verified
Multiple Choice
A) The higher the WACC used to calculate the NPV, the lower the calculated NPV will be.
B) If a project's NPV is greater than zero, then its IRR must be less than the WACC.
C) If a project's NPV is greater than zero, then its IRR must be less than zero.
D) The NPVs of relatively risky projects should be found using relatively low WACCs.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) The longer a project's payback period, the more desirable the project is normally considered to be by this criterion.
B) One drawback of the payback criterion for evaluating projects is that this method does not properly account for the time value of money.
C) If a project's payback is positive, then the project should be rejected because it must have a negative NPV.
D) The regular payback ignores cash flows beyond the payback period, but the discounted payback method overcomes this problem.
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) The MIRR and NPV decision criteria can never conflict.
B) The IRR method can never be subject to the multiple IRR problem, while the MIRR method can be.
C) One reason some people prefer the MIRR to the regular IRR is that the MIRR is based on what is generally a more reasonable assumption about the reinvestment rate than the regular IRR.
D) The higher the WACC, the shorter the discounted payback period.
Correct Answer
verified
Multiple Choice
A) A project's regular IRR is found by compounding the initial cost at the WACC to find the terminal value (TV) , then discounting the TV at the WACC.
B) A project's regular IRR is found by compounding the cash inflows at the WACC to find the present value (PV) , then discounting to find the IRR.
C) If a project's IRR is smaller than the WACC, then its NPV will be positive.
D) A project's IRR is the discount rate that causes the PV of the inflows to equal the project's cost.
Correct Answer
verified
Multiple Choice
A) The crossover rate between the two projects must be less than 10%.
B) The crossover rate between the two projects must be greater than 10%.
C) If the WACC is 8%, Project X will have the higher NPV.
D) If the WACC is 18%, Project Y will have the higher NPV.
Correct Answer
verified
Multiple Choice
A) One defect of the IRR method is that it does not take account of cash flows over a project's full life.
B) One defect of the IRR method is that it does not take account of the time value of money.
C) One defect of the IRR method is that it does not take account of the cost of capital.
D) One defect of the IRR method is that it does not assume that the cash flows to be received from a project can be reinvested at a rate other than the IRR itself.
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) The IRR method appeals to some managers because it gives an estimate of the rate of return on projects rather than a dollar amount, which the NPV method provides.
B) The discounted payback method eliminates all of the problems associated with the payback method.
C) When evaluating independent projects, the NPV and IRR methods often yield conflicting results regarding a project's acceptability.
D) To find the MIRR, we discount the TV at the IRR.
Correct Answer
verified
Multiple Choice
A) If Project A has a higher IRR than Project B, then Project A must have the lower NPV.
B) If Project A has a higher IRR than Project B, then Project A must also have a higher NPV.
C) The IRR calculation implicitly assumes that all cash flows are reinvested at the WACC.
D) If a project has normal cash flows and its IRR exceeds its WACC, then the project's NPV must be positive.
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Showing 1 - 20 of 69
Related Exams