Filters
Question type

Study Flashcards

The standard cost is a detailed estimate of how much a product should cost.

A) True
B) False

Correct Answer

verifed

verified

The budget procedure that requires all levels of management to start from zero in estimating sales, production, and other operating data is called zero-based budgeting.

A) True
B) False

Correct Answer

verifed

verified

If the expected sales volume for the current period is 7,000 units, the desired ending inventory is 400 units, and the beginning inventory is 300 units, the number of units set forth in the production budget, representing total production for the current period, is:


A) 6,900.
B) 7,000.
C) 7,200.
D) 7,100.

E) B) and D)
F) A) and B)

Correct Answer

verifed

verified

A variable cost system is an accounting system where standards are set for each manufacturing cost element.

A) True
B) False

Correct Answer

verifed

verified

McCabe Manufacturing Co.'s static budget at 8,000 units of production includes $40,000 for direct labor and $4,000 for electric power. Total fixed costs are $23,000. At 9,000 units of production, a flexible budget would show:


A) variable costs of $49,500 and $25,875 of fixed costs.
B) variable costs of $44,000 and $23,000 of fixed costs.
C) variable costs of $49,500 and $23,000 of fixed costs.
D) variable costs of $44,000 and $25,875 of fixed costs.

E) B) and D)
F) C) and D)

Correct Answer

verifed

verified

If the actual direct labor hours spent producing a commodity differ from the standard hours, the variance is termed:


A) time variance.
B) price variance.
C) quantity variance.
D) rate variance.

E) B) and D)
F) All of the above

Correct Answer

verifed

verified

The formula to compute direct material quantity variance is:


A) actual costs - standard costs.
B) standard costs - actual costs.
C) (actual quantity ´ standard price) - standard costs.
D) actual costs - (standard price ´ standard costs) .

E) B) and C)
F) None of the above

Correct Answer

verifed

verified

Kohlman Company began its operations on March 31 of the current year. Projected manufacturing costs for the first three months of business are $156,800, $195,200, and $217,600, respectively, for April, May, and June. Depreciation, insurance, and property taxes represent $28,800 of the estimated monthly manufacturing costs. Insurance was paid on March 31, and property taxes will be paid in November. Three-fourths of the remainder of the manufacturing costs are expected to be paid in the month in which they are incurred with the balance to be paid in the following month. Refer to the information provided for Kohlman Company. The cash payments for manufacturing in the month of May are:


A) $185,600.
B) $156,800.
C) $124,800.
D) $146,400.

E) All of the above
F) A) and B)

Correct Answer

verifed

verified

Which of the following conditions normally would not indicate that standard costs should be revised?


A) The engineering department has revised product specifications in responding to customer suggestions.
B) The company has signed a new union contract that increases the factory wages on average by $2.00 an hour.
C) Actual costs differed from standard costs for the preceding week.
D) The world price of raw materials increased.

E) A) and B)
F) A) and C)

Correct Answer

verifed

verified

The standard costs and actual costs for direct materials, direct labor, and factory overhead for the manufacture of 2,500 units of product are as follows:  Standard Costs 2,500 kilograms@$8 Direct material 7,500 hours @$12  Direct labor Actual Costs  2,600 kilograms@$8.75 Direct material  7,400 hours @ $ 11.40 Direct labor Factory overhead (100% capacity  10,000hrs) : \begin{array}{lrr} \text { Standard Costs } &\\ \text {2,500 kilograms@\$8 } & \text {Direct material}\\ \text { 7,500 hours @\$12 } & \text { Direct labor}\\\\ \text { Actual Costs } &\\ \text { 2,600 kilograms@\$8.75 } & \text {Direct material }\\ \text { 7,400 hours @ \$ 11.40 } & \text {Direct labor}\\\\ \text { Factory overhead (100\% capacity } &\\ \text { \( 10,000 \mathrm{hrs}) : \) } &\\\end{array} Variable cost @ $2 per hour Total variable cost, $18,000 Fixed cost @ $0.80 per hour Total fixed cost, $8,000 The amount of the fixed factory overhead volume variance is:


A) $2,000 favorable.
B) $2,500 favorable.
C) $2,500 unfavorable.
D) $2,000 unfavorable.

E) A) and B)
F) B) and D)

Correct Answer

verifed

verified

Cape Corporation sells a single product. Budgeted sales for the year are anticipated to be 640,000 units, estimated beginning inventory is 98,000 units, and desired ending inventory is 80,000 units. The quantities of direct materials expected to be used for each unit of finished product are given below. $0.60 per pound .50lb. per unit  Material A $1.70 per pound 1.00lb. per unit  Material B$1.00 per pound 1.20lb. per unit  Material C \begin{array}{lll}\$ 0.60 \text { per pound } & .50 \mathrm{lb} . \text { per unit } & \text { Material A } \\\$ 1.70 \text { per pound } & 1.00 \mathrm{lb} \text {. per unit } & \text { Material } \mathrm{B} \\\$ 1.00 \text { per pound } & 1.20 \mathrm{lb} . \text { per unit } & \text { Material C }\end{array} Refer to the information provided for Cape Corporation. The amount of direct material B purchased during the year is:


A) $1,224,000.
B) $1,390,600.
C) $1,088,000.
D) $1,057,400.

E) None of the above
F) A) and B)

Correct Answer

verifed

verified

Brown Inc.'s production budget for Product X for the year ended December 31 is as follows:  Product X640,000 units  Sales 85,000 Plus desired ending inventory 725,000 Total 90,000 Less estimated beginning inventory, Jan 1635,000 Total production \begin{array}{ll} \underline{\text { Product X} }\\640,000 \text { units }&\text { Sales } \\ \underline{85,000 }& \text { Plus desired ending inventory }\\ 725,000& \text { Total } \\ \underline{90,000}&\text { Less estimated beginning inventory, Jan 1} \\ \underline{ 635,000} & \text { Total production }\\ \end{array} In Brown's production operations, Materials A, B, and C are required to make Product X. The quantities of direct materials expected to be used for each unit of product are as follows: Product X Material A .50 pound per unit Material B 1.00 pound per unit Material C 1.20 pound per unit The prices of direct materials are as follows: Material A $0.60 per pound Material B $1.70 per pound Material C $1.50 per pound Prepare a direct materials purchases budget for Product X.

Correct Answer

verifed

verified

blured image Note A:
Material A 635,000 .5...

View Answer

Goal conflict can be avoided if budget goals are carefully designed for consistency across all areas of the organization.

A) True
B) False

Correct Answer

verifed

verified

The following data relate to direct labor costs for the current period of Executive Inc.: 6,000 hours at $12.00  Standard costs 7,500 hours at $11.60  Actual costs \begin{array}{lrr} \text {6,000 hours at \$12.00 } & \text { Standard costs } \\ \text {7,500 hours at \( \$ 11.60 \) } & \text { Actual costs } \\\end{array} Refer to the information provided for Executive Inc. What is the direct labor time variance?


A) $17,400 favorable
B) $17,400 unfavorable
C) $18,000 favorable
D) $18,000 unfavorable

E) B) and D)
F) A) and D)

Correct Answer

verifed

verified

Following is the information about Standard Inc. The standard costs and actual costs for direct materials, direct labor, and factory overhead for the manufacture of 2,500 units of product are as follows:  Standard Costs 2,500 kilograms@$8 Direct material 7,500 hours @$12  Direct labor Actual Costs  2,600 kilograms@$8.75 Direct material  7,400 hours @ $ 11.40 Direct labor Factory overhead (100% capacity  10,000hrs) : \begin{array}{lrr} \text { Standard Costs } &\\ \text {2,500 kilograms@\$8 } & \text {Direct material}\\ \text { 7,500 hours @\$12 } & \text { Direct labor}\\\\ \text { Actual Costs } &\\ \text { 2,600 kilograms@\$8.75 } & \text {Direct material }\\ \text { 7,400 hours @ \$ 11.40 } & \text {Direct labor}\\\\ \text { Factory overhead (100\% capacity } &\\ \text { \( 10,000 \mathrm{hrs}) : \) } &\\\end{array} Variable cost @ $2 per hour Total variable cost, $18,000 Fixed cost @ $0.80 per hour Total fixed cost, $8,000 Refer to the information provided for Standard Inc. The amount of the direct materials quantity variance is:


A) $875 favorable.
B) $875 unfavorable.
C) $800 favorable.
D) $800 unfavorable.

E) A) and C)
F) B) and C)

Correct Answer

verifed

verified

If the price paid per unit differs from the standard price per unit for direct materials, the variance is termed:


A) variable variance.
B) controllable variance.
C) price variance.
D) volume variance.

E) B) and D)
F) B) and C)

Correct Answer

verifed

verified

Standard and actual costs for direct materials for the manufacture of 1,000 units of product were as follows: 1,5501bs.@$9.10 Actual costs 1,6001bs.@$9.00 Standard costs \begin{array}{ll}1,5501 \mathrm{bs} .@ \$ 9.10 & \text { Actual costs } \\1,6001 \mathrm{bs} . @\$ 9.00 & \text { Standard costs }\end{array} Determine the (a) quantity variance, (b) price variance, and (c) total direct materials cost variance.

Correct Answer

verifed

verified

None...

View Answer

Nonmanufacturing activities are usually controlled using a static budget rather than a standard costing system.

A) True
B) False

Correct Answer

verifed

verified

If the standard to produce a given amount of product is 12,000 hours at a factory overhead rate of $5 ($3 fixed, $2 variable), actual variable factory overhead was $26,400, actual fixed factory overhead was $45,000, and 100% of productive capacity is 15,000 hours, the volume variance was $9,000 favorable.

A) True
B) False

Correct Answer

verifed

verified

Which of the following formula is used to calculate direct labor rate variance?


A) Actual Costs + (Actual hours ´ Standard Rate) .
B) Actual costs - Standard cost.
C) (Actual hours ´ Standard rate) - Standard costs.
D) Actual costs - (Actual hours ´ Standard rate) .

E) B) and D)
F) None of the above

Correct Answer

verifed

verified

Showing 141 - 160 of 168

Related Exams

Show Answer