Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) If two projects are mutually exclusive, then they are likely to have multiple IRRs.
B) If a project is independent, then it cannot have multiple IRRs.
C) Multiple IRRs can occur only if the signs of the cash flows change more than once.
D) If a project has two IRRs, then the smaller one is the one that is most relevant, and it should be accepted and relied upon.
E) For a project to have more than one IRR, then both IRRs must be greater than the cost of capital.
Correct Answer
verified
Multiple Choice
A) One advantage of the NPV over the IRR is that NPV assumes that cash flows will be reinvested at the cost of capital, whereas IRR assumes that cash flows are reinvested at the IRR. The NPV assumption is generally more appropriate.
B) One advantage of the NPV over the MIRR method is that NPV takes account of cash flows over a project's full life whereas MIRR does not.
C) One advantage of the NPV over the MIRR method is that NPV discounts cash flows whereas the MIRR is based on undiscounted cash flows.
D) Since cash flows under the IRR and MIRR are both discounted at the same rate (the cost of capital) , these two methods always rank mutually exclusive projects in the same order.
E) One advantage of the NPV over the IRR is that NPV takes account of cash flows over a project's full life whereas IRR does not.
Correct Answer
verified
Multiple Choice
A) One defect of the IRR method versus the NPV is that the IRR does not take account of the time value of money.
B) One defect of the IRR method versus the NPV is that the IRR does not take account of the cost of capital.
C) One defect of the IRR method versus the NPV is that the IRR values a dollar received today the same as a dollar that will not be received until sometime in the future.
D) One defect of the IRR method versus the NPV is that the IRR does not take proper account of differences in the sizes of projects.
E) One defect of the IRR method versus the NPV is that the IRR does not take account of cash flows over a project's full life.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) −$18.89
B) −$19.88
C) −$20.93
D) −$22.03
E) −$23.13
Correct Answer
verified
Multiple Choice
A) $188.68
B) $198.61
C) $209.07
D) $219.52
E) $230.49
Correct Answer
verified
Multiple Choice
A) The payback method is generally regarded by academics as being the best single method for evaluating capital budgeting projects.
B) The discounted payback method is generally regarded by academics as being the best single method for evaluating capital budgeting projects.
C) The net present value method (NPV) is generally regarded by academics as being the best single method for evaluating capital budgeting projects.
D) The modified internal rate of return method (MIRR) is generally regarded by academics as being the best single method for evaluating capital budgeting projects.
E) The internal rate of return method (IRR) is generally regarded by academics as being the best single method for evaluating capital budgeting projects.
Correct Answer
verified
Multiple Choice
A) If Project A's IRR exceeds Project B's, then A must have the higher NPV.
B) A project's MIRR can never exceed its IRR.
C) If a project with normal cash flows has an IRR less than the cost of capital, the project must have a positive NPV.
D) If the NPV is negative, the IRR must also be negative.
E) If a project with normal cash flows has an IRR greater than the cost of capital, the project must also have a positive NPV.
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) 1.61 years
B) 1.79 years
C) 1.99 years
D) 2.22 years
E) 2.44 years
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) The IRR method can never be subject to the multiple IRR problem, while the MIRR method can be.
B) One reason some people prefer the MIRR to the regular IRR is that the MIRR is based on a generally more reasonable reinvestment rate assumption.
C) The higher the cost of capital, the shorter the discounted payback period.
D) The MIRR method assumes that cash flows are reinvested at the crossover rate.
E) The MIRR and NPV decision criteria can never conflict.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) The crossover rate must be greater than 10%.
B) If the cost of capital is 8%, Project X will have the higher NPV.
C) If the cost of capital is 18%, Project Y will have the higher NPV.
D) Project X is larger in the sense that it has the higher initial cost.
E) The crossover rate must be less than 10%.
Correct Answer
verified
Multiple Choice
A) 9.43%
B) 9.91%
C) 10.40%
D) 10.92%
E) 11.47%
Correct Answer
verified
Multiple Choice
A) One drawback of the regular payback for evaluating projects is that this method does not properly account for the time value of money.
B) If a project's payback is positive, then the project should be rejected because it must have a negative NPV.
C) The regular payback ignores cash flows beyond the payback period, but the discounted payback method overcomes this problem.
D) If a company uses the same payback requirement to evaluate all projects, say it requires a payback of 4 years or less, then the company will tend to reject projects with relatively short lives and accept long-lived projects, and this will cause its risk to increase over time.
E) The longer a project's payback period, the more desirable the project is normally considered to be by this criterion.
Correct Answer
verified
True/False
Correct Answer
verified
Showing 81 - 100 of 108
Related Exams