Correct Answer
verified
Multiple Choice
A) You should delay a decision until you have more information on the projects, even if this means that a competitor might come in and capture this market.
B) You should recommend Project R, because at the new WACC it will have the higher NPV.
C) You should recommend Project K, because at the new WACC it will have the higher NPV.
D) You should recommend Project R because it will have both a higher IRR and a higher NPV under the new conditions.
E) You should reject both projects because they will both have negative NPVs under the new conditions.
Correct Answer
verified
Multiple Choice
A) $77.49
B) $81.56
C) $85.86
D) $90.15
E) $94.66
Correct Answer
verified
Multiple Choice
A) 1.61 years
B) 1.79 years
C) 1.99 years
D) 2.22 years
E) 2.44 years
Correct Answer
verified
Multiple Choice
A) You should recommend that the project be rejected because, although its NPV is positive, it has an IRR that is less than the WACC.
B) You should recommend that the project be accepted because (1) its NPV is positive and (2) although it has two IRRs, in this case it would be better to focus on the MIRR, which exceeds the WACC. You should explain this to the president and tell him that the firm's value will increase if the project is accepted.
C) You should recommend that the project be rejected. Although its NPV is positive it has two IRRs, one of which is less than the WACC, which indicates that the firm's value will decline if the project is accepted.
D) You should recommend that the project be rejected because, although its NPV is positive, its MIRR is less than the WACC, and that indicates that the firm's value will decline if it is accepted.
E) You should recommend that the project be rejected because its NPV is negative and its IRR is less than the WACC.
Correct Answer
verified
Multiple Choice
A) $250.15
B) $277.94
C) $305.73
D) $336.31
E) $369.94
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) 13.42%
B) 14.91%
C) 16.56%
D) 18.22%
E) 20.04%
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) 13.13%
B) 14.44%
C) 15.89%
D) 17.48%
E) 19.22%
Correct Answer
verified
Multiple Choice
A) If the WACC is 9%, Project A's NPV will be higher than Project B's.
B) If the WACC is 6%, Project B's NPV will be higher than Project A's.
C) If the WACC is greater than 14%, Project A's IRR will exceed Project B's.
D) If the WACC is 9%, Project B's NPV will be higher than Project A's.
E) If the WACC is 13%, Project A's NPV will be higher than Project B's.
Correct Answer
verified
Multiple Choice
A) $11.45
B) $12.72
C) $14.63
D) $16.82
E) $19.35
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) The NPV profile graph for a normal project will generally have a positive (upward) slope as the life of the project increases.
B) An NPV profile graph is designed to give decision makers an idea about how a project's risk varies with its life.
C) An NPV profile graph is designed to give decision makers an idea about how a project's contribution to the firm's value varies with the cost of capital.
D) We cannot draw a project's NPV profile unless we know the appropriate WACC for use in evaluating the project's NPV.
E) An NPV profile graph shows how a project's payback varies as the cost of capital changes.
Correct Answer
verified
Multiple Choice
A) 2.03 years
B) 2.25 years
C) 2.50 years
D) 2.75 years
E) 3.03 years
Correct Answer
verified
Multiple Choice
A) To find the MIRR, we first compound cash flows at the regular IRR to find the TV, and then we discount the TV at the WACC to find the PV.
B) The NPV and IRR methods both assume that cash flows can be reinvested at the WACC. However, the MIRR method assumes reinvestment at the MIRR itself.
C) If two projects have the same cost, and if their NPV profiles cross in the upper right quadrant, then the project with the higher IRR probably has more of its cash flows coming in the later years.
D) If two projects have the same cost, and if their NPV profiles cross in the upper right quadrant, then the project with the lower IRR probably has more of its cash flows coming in the later years.
E) For a project with normal cash flows, any change in the WACC will change both the NPV and the IRR.
Correct Answer
verified
Showing 41 - 60 of 107
Related Exams