The interval from the time of submission of a process to the time of completion is termed as


A) waiting time
B) turnaround time
C) response time
D) throughput

E) A) and B)
F) A) and C)

Correct Answer

verifed

verified

Which module gives control of the CPU to the process selected by the short-term scheduler?


A) dispatcher
B) interrupt
C) scheduler
D) none of the mentioned

E) A) and B)
F) B) and D)

Correct Answer

verifed

verified

Time quantum is defined in


A) shortest job scheduling algorithm
B) round robin scheduling algorithm
C) priority scheduling algorithm
D) multilevel queue scheduling algorithm

E) None of the above
F) C) and D)

Correct Answer

verifed

verified