A) You should reject both projects because they will both have negative NPVs under the new conditions.
B) You should delay a decision until you have more information on the projects, even if this means that a competitor might come in and capture this market.
C) You should recommend Project L, because at the new WACC it will have the higher NPV.
D) You should recommend Project S, because at the new WACC it will have the higher NPV.
E) You should recommend Project L because it will have both a higher IRR and a higher NPV under the new conditions.
Correct Answer
verified
Multiple Choice
A) Lacks an objective, market-determined benchmark for making decisions.
B) Ignores cash flows beyond the payback period.
C) Does not directly account for the time value of money.
D) Does not provide any indication regarding a project's liquidity or risk.
E) Does not take account of differences in size among projects.
Correct Answer
verified
Multiple Choice
A) An NPV profile graph shows how a project's payback varies as the cost of capital changes.
B) The NPV profile graph for a normal project will generally have a positive (upward) slope as the life of the project increases.
C) An NPV profile graph is designed to give decision makers an idea about how a project's risk varies with its life.
D) An NPV profile graph is designed to give decision makers an idea about how a project's contribution to the firm's value varies with the cost of capital.
E) We cannot draw a project's NPV profile unless we know the appropriate WACC for use in evaluating the project's NPV.
Correct Answer
verified
Multiple Choice
A) If a project with normal cash flows has an IRR greater than the WACC, the project must also have a positive NPV.
B) If Project A's IRR exceeds Project B's, then A must have the higher NPV.
C) A project's MIRR can never exceed its IRR.
D) If a project with normal cash flows has an IRR less than the WACC, the project must have a positive NPV.
E) If the NPV is negative, the IRR must also be negative.
Correct Answer
verified
Short Answer
Correct Answer
verified
Short Answer
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) A project's NPV is generally found by compounding the cash inflows at the WACC to find the terminal value (TV) , then discounting the TV at the IRR to find its PV.
B) The higher the WACC used to calculate the NPV, the lower the calculated NPV will be.
C) If a project's NPV is greater than zero, then its IRR must be less than the WACC.
D) If a project's NPV is greater than zero, then its IRR must be less than zero.
E) The NPVs of relatively risky projects should be found using relatively low WACCs.
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) Project S must have a higher NPV than Project L.
B) If Project S has a positive NPV, Project L must also have a positive NPV.
C) If the WACC falls, each project's IRR will increase.
D) If the WACC increases, each project's IRR will decrease.
E) If Projects S and L have the same NPV at the current WACC, 10%, then Project L, the one with the lower IRR, would have a higher NPV if the WACC used to evaluate the projects declined.
Correct Answer
verified
Multiple Choice
A) Project S.
B) Project L.
C) Both projects are equally sensitive to changes in the WACC since their NPVs are equal at all costs of capital.
D) Neither project is sensitive to changes in the discount rate, since both have NPV profiles that are horizontal.
E) The solution cannot be determined because the problem gives us no information that can be used to determine the projects' relative IRRs.
Correct Answer
verified
Short Answer
Correct Answer
verified
Short Answer
Correct Answer
verified
Multiple Choice
A) The NPV method assumes that cash flows will be reinvested at the WACC, while the IRR method assumes reinvestment at the IRR.
B) The NPV method assumes that cash flows will be reinvested at the risk-free rate, while the IRR method assumes reinvestment at the IRR.
C) The NPV method assumes that cash flows will be reinvested at the WACC, while the IRR method assumes reinvestment at the risk-free rate.
D) The NPV method does not consider all relevant cash flows, particularly cash flows beyond the payback period.
E) The IRR method does not consider all relevant cash flows, particularly cash flows beyond the payback period.
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) The shorter a project's payback period, the less desirable the project is normally considered to be by this criterion.
B) One drawback of the payback criterion is that this method does not take account of cash flows beyond the payback period.
C) If a project's payback is positive, then the project should be accepted because it must have a positive NPV.
D) The regular payback ignores cash flows beyond the payback period, but the discounted payback method overcomes this problem.
E) One drawback of the discounted payback is that this method does not consider the time value of money, while the regular payback overcomes this drawback.
Correct Answer
verified
True/False
Correct Answer
verified
Short Answer
Correct Answer
verified
Showing 61 - 80 of 94
Related Exams