A) 15.45%
B) 17.17%
C) 13.74%
D) 15.61%
E) 12.96%
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) An NPV profile graph shows how a project's payback varies as the cost of capital changes.
B) The NPV profile graph for a normal project will generally have a positive (upward) slope as the life of the project increases.
C) An NPV profile graph is designed to give decision makers an idea about how a project's risk varies with its life.
D) An NPV profile graph is designed to give decision makers an idea about how a project's contribution to the firm's value varies with the cost of capital.
E) We cannot draw a project's NPV profile unless we know the appropriate WACC for use in evaluating the project's NPV.
Correct Answer
verified
Multiple Choice
A) $73.38
B) $79.56
C) $0.00
D) $96.55
E) $78.01
Correct Answer
verified
Multiple Choice
A) If the two projects' NPV profiles do not cross,then there will be a sharp conflict as to which one should be selected.
B) If the cost of capital is greater than the crossover rate,then the IRR and the NPV criteria will not result in a conflict between the projects.One project will rank higher by both criteria.
C) If the cost of capital is less than the crossover rate,then the IRR and the NPV criteria will not result in a conflict between the projects.One project will rank higher by both criteria.
D) For a conflict to exist between NPV and IRR,the initial investment cost of one project must exceed the cost of the other.
E) For a conflict to exist between NPV and IRR,one project must have an increasing stream of cash flows over time while the other has a decreasing stream.If both sets of cash flows are increasing or decreasing,then it would be impossible for a conflict to exist,even if one project is larger than the other.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) $188.91
B) $145.46
C) $228.58
D) $226.70
E) $230.47
Correct Answer
verified
Multiple Choice
A) The crossover rate for the two projects must be less than 12%.
B) Assuming the timing pattern of the two projects' cash flows is the same,Project B probably has a higher cost (and larger scale) .
C) Assuming the two projects have the same scale,Project B probably has a faster payback than Project A.
D) The crossover rate for the two projects must be 12%.
E) Since B has the higher IRR,then it must also have the higher NPV if the crossover rate is less than the WACC of 12%.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) -$106.10
B) -$132.63
C) -$139.26
D) -$125.99
E) -$165.78
Correct Answer
verified
Multiple Choice
A) You should reject both projects because they will both have negative NPVs under the new conditions.
B) You should delay a decision until you have more information on the projects,even if this means that a competitor might come in and capture this market.
C) You should recommend Project L,because at the new WACC it will have the higher NPV.
D) You should recommend Project S,because at the new WACC it will have the higher NPV.
E) You should recommend Project L because it will have both a higher IRR and a higher NPV under the new conditions.
Correct Answer
verified
Multiple Choice
A) 0$286.36
B) 0$294.95
C) 0$349.36
D) 0$309.27
E) 0$355.08
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) $62.75
B) $59.20
C) $53.28
D) $51.51
E) $65.71
Correct Answer
verified
Multiple Choice
A) 0120.01
B) 0135.20
C) 0151.91
D) 0179.26
E) 0133.68
Correct Answer
verified
True/False
Correct Answer
verified
Showing 1 - 20 of 107
Related Exams