A) A project's NPV is found by compounding the cash inflows at the IRR to find the terminal value (TV) , then discounting the TV at the WACC.
B) The lower the WACC used to calculate it, the lower the calculated NPV will be.
C) If a project's NPV is less than zero, then its IRR must be less than the WACC.
D) If a project's NPV is greater than zero, then its IRR must be less than zero.
E) The NPV of a relatively low-risk project should be found using a relatively high WACC.
Correct Answer
verified
Multiple Choice
A) Lacks an objective, market-determined benchmark for making decisions.
B) Ignores cash flows beyond the payback period.
C) Does not directly account for the time value of money.
D) Does not provide any indication regarding a project's liquidity or risk.
E) Does not take account of differences in size among projects.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) Project S must have a higher NPV than Project L.
B) If Project S has a positive NPV, Project L must also have a positive NPV.
C) If the WACC falls, each project's IRR will increase.
D) If the WACC increases, each project's IRR will decrease.
E) If Projects S and L have the same NPV at the current WACC, 10%, then Project L, the one with the lower IRR, would have a higher NPV if the WACC used to evaluate the projects declined.
Correct Answer
verified
Multiple Choice
A) You should recommend that the project be rejected because its NPV is negative and its IRR is less than the WACC.
B) You should recommend that the project be rejected because, although its NPV is positive, it has an IRR that is less than the WACC.
C) You should recommend that the project be accepted because (1) its NPV is positive and (2) although it has two IRRs, in this case it would be better to focus on the MIRR, which exceeds the WACC. You should explain this to the president and tell him that that the firm's value will increase if the project is accepted.
D) You should recommend that the project be rejected because (1) its NPV is positive and (2) it has two IRRs, one of which is less than the WACC, which indicates that the firm's value will decline if the project is accepted.
E) You should recommend that the project be rejected because, although its NPV is positive, its MIRR is less than the WACC, and that indicates that the firm's value will decline if it is accepted.
Correct Answer
verified
Multiple Choice
A) The IRR method appeals to some managers because it gives an estimate of the rate of return on projects rather than a dollar amount, which the NPV method provides.
B) The discounted payback method eliminates all of the problems associated with the payback method.
C) When evaluating independent projects, the NPV and IRR methods often yield conflicting results regarding a project's acceptability.
D) To find the MIRR, we discount the TV at the IRR.
E) A project's NPV profile must intersect the X-axis at the project's WACC.
Correct Answer
verified
Multiple Choice
A) A project's MIRR is always greater than its regular IRR.
B) A project's MIRR is always less than its regular IRR.
C) If a project's IRR is greater than its WACC, then the MIRR will be less than the IRR.
D) If a project's IRR is greater than its WACC, then the MIRR will be greater than the IRR.
E) To find a project's MIRR, we compound cash inflows at the IRR and then discount the terminal value back to t = 0 at the WACC.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) A project's regular IRR is found by compounding the cash inflows at the WACC to find the terminal value (TV) , then discounting this TV at the WACC.
B) A project's regular IRR is found by discounting the cash inflows at the WACC to find the present value (PV) , then compounding this PV to find the IRR.
C) If a project's IRR is greater than the WACC, then its NPV must be negative.
D) To find a project's IRR, we must solve for the discount rate that causes the PV of the inflows to equal the PV of the project's costs.
E) To find a project's IRR, we must find a discount rate that is equal to the WACC.
Correct Answer
verified
Multiple Choice
A) If the WACC is 10%, both projects will have positive NPVs.
B) If the WACC is 6%, Project S will have the higher NPV.
C) If the WACC is 13%, Project S will have the lower NPV.
D) If the WACC is 10%, both projects will have a negative NPV.
E) Project S's NPV is more sensitive to changes in WACC than Project L's.
Correct Answer
verified
Multiple Choice
A) A project's MIRR is always greater than its regular IRR.
B) A project's MIRR is always less than its regular IRR.
C) If a project's IRR is greater than its WACC, then its MIRR will be greater than the IRR.
D) To find a project's MIRR, we compound cash inflows at the regular IRR and then find the discount rate that causes the PV of the terminal value to equal the initial cost.
E) To find a project's MIRR, the textbook procedure compounds cash inflows at the WACC and then finds the discount rate that causes the PV of the terminal value to equal the initial cost.
Correct Answer
verified
Multiple Choice
A) One advantage of the NPV over the IRR is that NPV takes account of cash flows over a project's full life whereas IRR does not.
B) One advantage of the NPV over the IRR is that NPV assumes that cash flows will be reinvested at the WACC, whereas IRR assumes that cash flows are reinvested at the IRR. The NPV assumption is generally more appropriate.
C) One advantage of the NPV over the MIRR method is that NPV takes account of cash flows over a project's full life whereas MIRR does not.
D) One advantage of the NPV over the MIRR method is that NPV discounts cash flows whereas the MIRR is based on undiscounted cash flows.
E) Since cash flows under the IRR and MIRR are both discounted at the same rate (the WACC) , these two methods always rank mutually exclusive projects in the same order.
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) Since the smaller project has the higher IRR, the two projects' NPV profiles cannot cross, and the smaller project's NPV will be higher at all positive values of WACC.
B) Since the smaller project has the higher IRR, the two projects' NPV profiles will cross, and the larger project will look better based on the NPV at all positive values of WACC.
C) If the company uses the NPV method, it will tend to favor smaller, shorter-term projects over larger, longer-term projects, regardless of how high or low the WACC is.
D) Since the smaller project has the higher IRR but the larger project has the higher NPV at a zero discount rate, the two projects' NPV profiles will cross, and the larger project will have the higher NPV if the WACC is less than the crossover rate.
E) Since the smaller project has the higher IRR and the larger NPV at a zero discount rate, the two projects' NPV profiles will cross, and the smaller project will look better if the WACC is less than the crossover rate.
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) The regular payback method recognizes all cash flows over a project's life.
B) The discounted payback method recognizes all cash flows over a project's life, and it also adjusts these cash flows to account for the time value of money.
C) The regular payback method was, years ago, widely used, but virtually no companies even calculate the payback today.
D) The regular payback is useful as an indicator of a project's liquidity because it gives managers an idea of how long it will take to recover the funds invested in a project.
E) The regular payback does not consider cash flows beyond the payback year, but the discounted payback overcomes this defect.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) A project's NPV is generally found by compounding the cash inflows at the WACC to find the terminal value (TV) , then discounting the TV at the IRR to find its PV.
B) The higher the WACC used to calculate the NPV, the lower the calculated NPV will be.
C) If a project's NPV is greater than zero, then its IRR must be less than the WACC.
D) If a project's NPV is greater than zero, then its IRR must be less than zero.
E) The NPVs of relatively risky projects should be found using relatively low WACCs.
Correct Answer
verified
Showing 1 - 20 of 72
Related Exams