Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) It will accept too many short-term projects and reject too many long-term projects (as judged by the NPV) .
B) It will accept too many long-term projects and reject too many short-term projects (as judged by the NPV) .
C) The firm will accept too many projects in all economic states because a 4-year payback is too low.
D) The firm will accept too few projects in all economic states because a 4-year payback is too high.
E) If the 4-year payback results in accepting just the right set of projects under average economic conditions, then this payback will result in too few long-term projects when the economy is weak.
Correct Answer
verified
Multiple Choice
A) $134.79
B) $141.89
C) $149.36
D) $164.29
E) $205.36
Correct Answer
verified
Multiple Choice
A) $41.25
B) $45.84
C) $50.93
D) $56.59
E) $62.88
Correct Answer
verified
Multiple Choice
A) $188.68
B) $198.61
C) $209.07
D) $219.52
E) $230.49
Correct Answer
verified
Multiple Choice
A) A project's regular IRR is found by compounding the cash inflows at the WACC to find the terminal value (TV) , then discounting this TV at the WACC.
B) A project's regular IRR is found by discounting the cash inflows at the WACC to find the present value (PV) , then compounding this PV to find the IRR.
C) If a project's IRR is greater than the WACC, then its NPV must be negative.
D) To find a project's IRR, we must solve for the discount rate that causes the PV of the inflows to equal the PV of the project's costs.
E) To find a project's IRR, we must find a discount rate that is equal to the WACC.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) 1.88 years
B) 2.09 years
C) 2.29 years
D) 2.52 years
E) 2.78 years
Correct Answer
verified
Multiple Choice
A) A project's NPV is found by compounding the cash inflows at the IRR to find the terminal value (TV) , then discounting the TV at the WACC.
B) The lower the WACC used to calculate it, the lower the calculated NPV will be.
C) If a project's NPV is less than zero, then its IRR must be less than the WACC.
D) If a project's NPV is greater than zero, then its IRR must be less than zero.
E) The NPV of a relatively low-risk project should be found using a relatively high WACC.
Correct Answer
verified
Multiple Choice
A) 8.86%
B) 9.84%
C) 10.94%
D) 12.15%
E) 13.50%
Correct Answer
verified
Multiple Choice
A) A project's MIRR is always greater than its regular IRR.
B) A project's MIRR is always less than its regular IRR.
C) If a project's IRR is greater than its WACC, then its MIRR will be greater than the IRR.
D) To find a project's MIRR, we compound cash inflows at the regular IRR and then find the discount rate that causes the PV of the terminal value to equal the initial cost.
E) To find a project's MIRR, the textbook procedure compounds cash inflows at the WACC and then finds the discount rate that causes the PV of the terminal value to equal the initial cost.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) 9.70%
B) 10.78%
C) 11.98%
D) 13.31%
E) 14.64%
Correct Answer
verified
Multiple Choice
A) $24.14
B) $26.82
C) $29.80
D) $33.11
E) $36.42
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) 12.55%
B) 13.21%
C) 13.87%
D) 14.56%
E) 15.29%
Correct Answer
verified
Multiple Choice
A) The shorter a project's payback period, the less desirable the project is normally considered to be by this criterion.
B) One drawback of the payback criterion is that this method does not take account of cash flows beyond the payback period.
C) If a project's payback is positive, then the project should be accepted because it must have a positive NPV.
D) The regular payback ignores cash flows beyond the payback period, but the discounted payback method overcomes this problem.
E) One drawback of the discounted payback is that this method does not consider the time value of money, while the regular payback overcomes this drawback.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) The NPV method was once the favorite of academics and business executives, but today most authorities regard the MIRR as being the best indicator of a project's profitability.
B) If the cost of capital declines, this lowers a project's NPV.
C) The NPV method is regarded by most academics as being the best indicator of a project's profitability, hence most academics recommend that firms use only this one method and disregard other methods.
D) A project's NPV depends on the total amount of cash flows the project produces, but because the cash flows are discounted at the WACC, it does not matter if the cash flows occur early or late in the project's life.
E) The NPV and IRR methods may give different recommendations regarding which of two mutually exclusive projects should be accepted, but they always give the same recommendation regarding the acceptability of a normal, independent project.
Correct Answer
verified
Showing 1 - 20 of 107